HRC’s scope of works and services for the project are planned to be undertaken in the
following manner:
? Rolling stock units will be supplied by HRC in Korea (design in the R&D Centre in
Uiwang and manufacturing and testing in Changwon).
? Delivery of Rolling Stock from Korea (Masan Port) to Newcastle port and onwards
delivery to designated facility.
? Localised commissioning (in depot and on mainline) in Australia will be based out of
the Eveleigh commissioning facility (9 trainsets, subject to readiness of Kangy?Angy
by end of Dec’2018)
? Commissioning (in depot and on mainline) of remainder of fleet will be based out of
the Kangy?Angy maintenance facility.